Gov. Ricketts Announces Accelerated Construction Timeline for Lincoln South Beltway

Media Contacts:  

Eric Maher, Governor’s Office, 402-471-1974

Jeni Campana, Department of Transportation, 402-479-4512

 

Governor Ricketts with (from left to right) Senator Suzanne Geist, Senator Mike Hilgers, NDOT Director Schneweis, and Senator Curt Friesen at the news conference announcing the accelerated construction timeline of the Lincoln South Beltway. 

 

LINCOLN – Today, Governor Pete Ricketts, along with Senator Curt Friesen, Senator Suzanne Geist, Senator Mike Hilgers, Lincoln Mayor Chris Beutler, and Nebraska Department of Transportation Director (NDOT) Kyle Schneweis, announced an expedited construction schedule that will allow the Lincoln South Beltway to be open to traffic by the end of 2022. 

 

The Lincoln South Beltway will improve regional connectivity by creating an 11-mile east to west four-lane freeway south of Lincoln, linking Highway 77 and Nebraska Highway 2.  It is designed to reduce conflicts between local and through traffic, including heavy truck traffic.

 

“Today, we are excited to announce that the long-awaited Lincoln South Beltway project will be constructed ahead of schedule,” said Governor Ricketts.  “This is another example of using innovation to make the state’s operations more efficient, so we can grow Nebraska and keep Lincoln moving.” 

 

“This project has been a priority for Lincoln and Lancaster County for years,” said Senator Hilgers.  “Today's announcement is a big step forward to making the South Beltway a reality.  I’m happy to be part of the solution to bring it to Nebraskans by the end of 2022.”

 

“This project provides the necessary capacity to the area to allow regional travelers an alternative route around Lincoln, reducing traffic through the city,” said Director Schneweis.  “The Lincoln South Beltway has been a project that has been well designed, discussed, and desired for many years.  We are happy to be able to finally bring it to Nebraskans.”  

 

Previously, construction was anticipated to take up to eight years to complete.  With this new approach, the NDOT will begin construction in 2020 and traffic will be underway on the Lincoln South Beltway by the end of 2022.